Baragine wind farm is currently under construction in the Marijampole district; it will consist of five modern Nordex wind turbines. Each turbine will have a capacity of 5.9 MW, bringing the wind farm’s total installed capacity to 29.5 MW. As of June 2026, access roads have been built, turbine foundations have been concreted, and electrical lines have been installed. These completed works demonstrate the project’s smooth progress and reduce the risk associated with the implementation of key construction stages. Construction of the Baragine wind farm is scheduled for completion in April 2027.

Project information

Year
2027
Place
Marijampole distr.
post23